Week 1CURRENT
Mar 9 – Mar 13
3
M
9
T
10
W
11
T
12
F
13
TAPING DRYWALL
ACTIVE
L2E
MAXUM
Start
Mar 4, 2026
Finish
Mar 24, 2026
Duration
15 bus. days
Days Remaining
12
business days
Progress0%
Next:PRIME & PAINT 1st COAT
PL
Last edited byPaul Labik
16h agoStarts Today
INSTALL T-BAR CEILING
ACTIVE
L2W
MAXUM
Start
Mar 9, 2026
Finish
Mar 20, 2026
Duration
10 bus. days
Days Remaining
10
business days
Progress0%
Next:PRIME & PAINT 1st COAT
PL
Last edited byPaul Labik
16h agoStarts Today
PRIME & PAINT 1st COAT
ACTIVE
L2E
CPE
Start
Mar 9, 2026
Finish
Mar 20, 2026
Duration
10 bus. days
Days Remaining
10
business days
Progress0%
Follows:TAPING DRYWALL
Next:INSTALL T-BAR CEILING
PL
Last edited byPaul Labik
15h agoWeek 2
Mar 16 – Mar 20
3
M
16
T
17
W
18
T
19
F
20
TAPING DRYWALL
ACTIVE
L2E
MAXUM
Start
Mar 4, 2026
Finish
Mar 24, 2026
Duration
15 bus. days
Days Remaining
12
business days
Progress0%
Next:PRIME & PAINT 1st COAT
PL
Last edited byPaul Labik
16h agoStarts Today
INSTALL T-BAR CEILING
ACTIVE
L2W
MAXUM
Start
Mar 9, 2026
Finish
Mar 20, 2026
Duration
10 bus. days
Days Remaining
10
business days
Progress0%
Next:PRIME & PAINT 1st COAT
PL
Last edited byPaul Labik
16h agoStarts Today
PRIME & PAINT 1st COAT
ACTIVE
L2E
CPE
Start
Mar 9, 2026
Finish
Mar 20, 2026
Duration
10 bus. days
Days Remaining
10
business days
Progress0%
Follows:TAPING DRYWALL
Next:INSTALL T-BAR CEILING
PL
Last edited byPaul Labik
15h agoWeek 3
Mar 23 – Mar 27
3
M
23
T
24
W
25
T
26
F
27
TAPING DRYWALL
ACTIVE
L2E
MAXUM
Start
Mar 4, 2026
Finish
Mar 24, 2026
Duration
15 bus. days
Days Remaining
12
business days
Progress0%
Next:PRIME & PAINT 1st COAT
PL
Last edited byPaul Labik
16h agoM/E DROPS TO T-BAR CEILINGS
NOT STARTED
L2W
LANDON
Start
Mar 23, 2026
Finish
Apr 10, 2026
Duration
15 bus. days
Not Started
--
starts in 10 days
Progress0%
Follows:INSTALL T-BAR CEILING
Next:INSTALL ACT
PL
Last edited byPaul Labik
16h agoM/E DROPS TO T-BAR CEILINGS
NOT STARTED
L2W
PHE
Start
Mar 23, 2026
Finish
Apr 10, 2026
Duration
15 bus. days
Not Started
--
starts in 10 days
Progress0%
Follows:INSTALL T-BAR CEILING
Next:INSTALL ACT
PL
Last edited byPaul Labik
16h agoWeek 4
Mar 30 – Apr 3
2
M
30
T
31
W
1
T
2
F
3
M/E DROPS TO T-BAR CEILINGS
NOT STARTED
L2W
LANDON
Start
Mar 23, 2026
Finish
Apr 10, 2026
Duration
15 bus. days
Not Started
--
starts in 10 days
Progress0%
Follows:INSTALL T-BAR CEILING
Next:INSTALL ACT
PL
Last edited byPaul Labik
16h agoM/E DROPS TO T-BAR CEILINGS
NOT STARTED
L2W
PHE
Start
Mar 23, 2026
Finish
Apr 10, 2026
Duration
15 bus. days
Not Started
--
starts in 10 days
Progress0%
Follows:INSTALL T-BAR CEILING
Next:INSTALL ACT
PL
Last edited byPaul Labik
16h ago