Look-Ahead Schedule — Last Planner System

HomeUpgrade
7Total
3Active
0At Risk
0Overdue
4Not Started
Week 1CURRENT
Mar 9 – Mar 13
3
M
9
T
10
W
11
T
12
F
13

TAPING DRYWALL

ACTIVE
L2E
MAXUM
Start
Mar 4, 2026
Finish
Mar 24, 2026
Duration
15 bus. days
Days Remaining
12
business days
Progress0%
Next:
PRIME & PAINT 1st COAT
PL
Last edited byPaul Labik
16h ago
Starts Today

INSTALL T-BAR CEILING

ACTIVE
L2W
MAXUM
Start
Mar 9, 2026
Finish
Mar 20, 2026
Duration
10 bus. days
Days Remaining
10
business days
Progress0%
Next:
PRIME & PAINT 1st COAT
PL
Last edited byPaul Labik
16h ago
Starts Today

PRIME & PAINT 1st COAT

ACTIVE
L2E
CPE
Start
Mar 9, 2026
Finish
Mar 20, 2026
Duration
10 bus. days
Days Remaining
10
business days
Progress0%
Follows:
TAPING DRYWALL
Next:
INSTALL T-BAR CEILING
PL
Last edited byPaul Labik
15h ago
Week 2
Mar 16 – Mar 20
3
M
16
T
17
W
18
T
19
F
20

TAPING DRYWALL

ACTIVE
L2E
MAXUM
Start
Mar 4, 2026
Finish
Mar 24, 2026
Duration
15 bus. days
Days Remaining
12
business days
Progress0%
Next:
PRIME & PAINT 1st COAT
PL
Last edited byPaul Labik
16h ago
Starts Today

INSTALL T-BAR CEILING

ACTIVE
L2W
MAXUM
Start
Mar 9, 2026
Finish
Mar 20, 2026
Duration
10 bus. days
Days Remaining
10
business days
Progress0%
Next:
PRIME & PAINT 1st COAT
PL
Last edited byPaul Labik
16h ago
Starts Today

PRIME & PAINT 1st COAT

ACTIVE
L2E
CPE
Start
Mar 9, 2026
Finish
Mar 20, 2026
Duration
10 bus. days
Days Remaining
10
business days
Progress0%
Follows:
TAPING DRYWALL
Next:
INSTALL T-BAR CEILING
PL
Last edited byPaul Labik
15h ago
Week 3
Mar 23 – Mar 27
3
M
23
T
24
W
25
T
26
F
27

TAPING DRYWALL

ACTIVE
L2E
MAXUM
Start
Mar 4, 2026
Finish
Mar 24, 2026
Duration
15 bus. days
Days Remaining
12
business days
Progress0%
Next:
PRIME & PAINT 1st COAT
PL
Last edited byPaul Labik
16h ago

M/E DROPS TO T-BAR CEILINGS

NOT STARTED
L2W
LANDON
Start
Mar 23, 2026
Finish
Apr 10, 2026
Duration
15 bus. days
Not Started
--
starts in 10 days
Progress0%
Follows:
INSTALL T-BAR CEILING
Next:
INSTALL ACT
PL
Last edited byPaul Labik
16h ago

M/E DROPS TO T-BAR CEILINGS

NOT STARTED
L2W
PHE
Start
Mar 23, 2026
Finish
Apr 10, 2026
Duration
15 bus. days
Not Started
--
starts in 10 days
Progress0%
Follows:
INSTALL T-BAR CEILING
Next:
INSTALL ACT
PL
Last edited byPaul Labik
16h ago
Week 4
Mar 30 – Apr 3
2
M
30
T
31
W
1
T
2
F
3

M/E DROPS TO T-BAR CEILINGS

NOT STARTED
L2W
LANDON
Start
Mar 23, 2026
Finish
Apr 10, 2026
Duration
15 bus. days
Not Started
--
starts in 10 days
Progress0%
Follows:
INSTALL T-BAR CEILING
Next:
INSTALL ACT
PL
Last edited byPaul Labik
16h ago

M/E DROPS TO T-BAR CEILINGS

NOT STARTED
L2W
PHE
Start
Mar 23, 2026
Finish
Apr 10, 2026
Duration
15 bus. days
Not Started
--
starts in 10 days
Progress0%
Follows:
INSTALL T-BAR CEILING
Next:
INSTALL ACT
PL
Last edited byPaul Labik
16h ago
Trades
CPE
LANDON
MAXUM
PHE
Schedule: Week of Mar 9, 2026 — Week of Mar 30, 2026Weekends excluded from all countdowns · Auto-refreshes every minuteMon, Mar 9, 2026